Project : Drainage and Concrete Works at Heineken Distilling Plant

This contract involved the installation of a new drainage system and floor in the main distilling plant at the Heineken plant in Cork City. Access was very confined and it was of utmost importance that the plant was kept operational during the construction works. All aspects of this project had to be carried out with the greatest of care as we were working in very close proximity to live gas, fluid and electrical lines. The works was executed within the tight programme and of most importance was completed without incident or accident.

Client: Heineken Group

Design Team: Heineken Clerk of Works

Value: €100,000

Duration: 2 months